CO129-341 - Acting Governor May Governor Lugard - 1907 [7-10] — Page 702

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All AI Reviewed

696

...

question of Tunnel contracts, vis.:- whether larger sections could be let to contract and whether real contracts as opposed to what I have called the "piece-work bargain system" could be usefully made, no definite conclusion was arrived at. Mr. Ives stated that no contractor would look at it. I requested the Hon. Director of Public Works to talk over the matter with some of the contractors whom he know, with a view to assisting the Government and the Chief Resident Engineer in this matter and to report the result. Generally speaking I gathered that the Hon. Director of Public Works was strongly of the opinion that the work outside the Tunnel should be let out to contractors in comparatively large contracts. In discussion with Messrs. Wolfe and Barry I gathered - I am not sure whether rightly - they were not at all averse to this. Mr. Eves on the other hand appears averse to such contracts and thinks he can do the work as quickly and more cheaply himself. Time is of course a very important question in the case of the Tunnel, and the capital cost of the whole line lies out at interest until it is completed.

4. Progress reports. I had pointed out in a minute that the present progress report deals only with the bottom heading, and therefore gives no real indication of the progress of the Tunnel, and I asked for an indication of the progress in the top heading and Facing. The Chief Resident Engineer pointed out that the two latter were identical, the Facing necessarily following the Top heading as soon as the shoring was removed. He saw some difficulty in shewing progress in this matter, but after a short discussion a scheme was arrived at, which he considered quite feasible and involving no trouble, by which he would report the weekly progress in the lengths of lining actually completed.

5.

Mr. Ives raised the question of the Hongkong-Kowloon Ferry. He said that he was now preparing the Supplemental Estimates and must know whether or not to include a wharf for steamers and cost of Steamers. That the latter would take 2 or 3 years to...

Edit History

2026-06-05 12:59:11 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
696 ... question of Tunnel contracts, vis.:- whether larger sections could be let to contract and whether real contracts as opposed to what I have called the "piece-work bargain system" could be usefully made, no definite conclusion was arrived at. Mr. Ives stated that no contractor would look at it. I requested the Hon. Director of Public Works to talk over the matter with some of the contractors whom he know, with a view to assisting the Government and the Chief Resident Engineer in this matter and to report the result. Generally speaking I gathered that the Hon. Director of Public Works was strongly of the opinion that the work outside the Tunnel should be let out to contractors in comparatively large contracts. In discussion with Messrs. Wolfe and Barry I gathered - I am not sure whether rightly - they were not at all averse to this. Mr. Eves on the other hand appears averse to such contracts and thinks he can do the work as quickly and more cheaply himself. Time is of course a very important question in the case of the Tunnel, and the capital cost of the whole line lies out at interest until it is completed. 4. Progress reports. I had pointed out in a minute that the present progress report deals only with the bottom heading, and therefore gives no real indication of the progress of the Tunnel, and I asked for an indication of the progress in the top heading and Facing. The Chief Resident Engineer pointed out that the two latter were identical, the Facing necessarily following the Top heading as soon as the shoring was removed. He saw some difficulty in shewing progress in this matter, but after a short discussion a scheme was arrived at, which he considered quite feasible and involving no trouble, by which he would report the weekly progress in the lengths of lining actually completed. 5. Mr. Ives raised the question of the Hongkong-Kowloon Ferry. He said that he was now preparing the Supplemental Estimates and must know whether or not to include a wharf for steamers and cost of Steamers. That the latter would take 2 or 3 years to...
Baseline (Original)
696 of abla racitte beIdane majeṣa molton a'xoow art bas,betiɛoqeb esetq $namesq to madaya a recitat dost at at #1 .stanterist -tnatenco seiner Know adid, to erðan sɗif ‚†ostinoo a nadé drOW kar ezerit nerw ynthæon qot edit al dittw tem gated X00%) [X- anoereq saedt as bas (no oa bna galbeed mottod edit ni enog mojaye Źow obsig midi iquons ɑriw auantriɔ to naeqoruƐ sOKËT SHËN (y[Xoow) traupert at vino for lætigao on dółw sem yalirow sta 11 aud Įnam nions yaq Yam yoďð takið rebro al viaassoan inamyaq bezeler fæum varied acid äthy ömer al olvaduɗo betɔeqesno Tas Tekno ent .asoi edd brotts Jon bingo 'rodbørðnað! exit vot anissa ni brød reart a bebrææeb exoterend TeeniyaM taoblenk bentaiqmo bra (*ados"dnoð" borunaim) anlægtað Frow-eosiq saed? -revo bna shnad aid sit of sa down saw tibus to undera odið tært -aunod evig sids bertasb of „Erow Hood dółw mid nobruË= sageront bus anoitibnoo xalet of snorgotq batarefèone not g#- IlbWA Jædt bentu ek ‚„boneteter duod÷iw vissesoen ti dnompaq- od sidaoliqqs don stew suneve♬ mort sÍïow oð: sĹdiamÅÍÇÜB, RBLIT Smerettib yllodw alkol mi færið bra tavonsk (aðiqað morŤ KÍTOW ort bentevon doldw snodt mort samo eno edt al sdam stew solut .Tenfo arið ðærið beðneygon axrow olidut to rodoerta „noĦ sdt rot noqu boeiga mue arið saman blvode "eenkyni inobisef teiɗo -yaq sɗd to esmeroni yna berinob od 21 Jaɗd bns Xrow-boniq edit TonTerol edt bevorgqs Joette Jædd of noltabnemeooer #: #NGES»» darið beerga I „aðnemarłuper a1rotibʊå ødt tot soittum bluow beouber bĺneo Xow Isoireio Visessoennu doldw yd aNGGET VILS orutammin edt tærit ennatani tot qilatosque (sidariaab tingið s to toot, ant da reoltto:eidianoqesi s to (ndasititres a teva) aút gat-luper to bɛetani inaloittaa new stewodai to Ilơ% vaq er modeva rattal sɗt no beabnt fool I „eðstoðkift done to f{"cate JI .noaneq Inelubuætt a no Esedo a to bastani od dnsamoubat na ert bra tervaasi? „noë eds of taloq aint retot of bestga naw of batqoba ad trişim'ensem fariv ot na troqet not notibwa Imooi veɗt .Írow gnitnwooda souber bra afnemertuper a'aav£ .TX Joom lazsneg #tom edd no „min d3tw divanos od siguone boog ed IIIw nolJesup question of Tunnel contracts, vis.:- whether larger sections could be let to contract and whether real contracts as opposed to what I have called the "piece-work bargain system" could be usefully made, no definite conclusion was arrived at. Mr. Ives stated that no contractor would look at it. I requested the Hon. Director of Public Works to talk over the matter with'some of the contractors whom he know, with a view to assisting the #overnment and the Chief Resident Engineer in this matter and to report the result. Generally speaking I gathered that the Mon. Director of Public Works was strongly of the opinion that the work outside the Tunnel should be let out to contractors in comparatively large contracts. In discussion with Messrs. Wolfe and Barry I gathered -I am not sure whether 'rightly they were not at all averse to this. Mr. Eves on the other hand appears averse to such contracts and thinks he can do the work as quickly and more cheaply himself. Time is of course a very important question in the case of the Tunnel, and the capital cost of the whole line lies out at interest until it is comTM -pleted. that 4. Progress reports. I had pointed out in a minute that the present progress report deals only with the bottom heading, and therefore gives no real indication of the progress of the Tunnel, and I asked for an indication of the progress in the top heading and Facing. The Chief Resident Engineer pointed out that the two latter were identical, the Facing necessarily following the Top heading as soon as the shoring was removed. He saw some difficulty in shewing progress in this matter, but after a short discussion a scheme was arrived at, which he considered quite feasible and involving no trouble, by which he would report the weekly progress in the lengths of lining actually completed. 5. Kr. Ives raised the question of the Hongkong-Kowloon Ferry. He said that he was now preparing the Supplemental Estimates and must know whether or not to include a wharf for steamers and cost of Steamers. That the latter would take 2 or 3 years to
2026-06-05 12:59:11 · Baseline
View content

696

of abla racitte beIdane majeṣa molton a'xoow art bas,betiɛoqeb

esetq yď $namesq to madaya a recitat dost at at #1 .stanterist

-tnatenco seiner Know adid, to erðan sɗif nÀ ‚†ostinoo a nadé drOW

kar ezerit nerw ynthæon qot edit al dittw tem gated X00%) [X-

anoereq saedt as bas (no oa bna galbeed mottod edit ni enog

mojaye Źow obsig midi iquons ɑriw auantriɔ to naeqoruƐ sOKËT SHËN

(y[Xoow) traupert at vino for lætigao on dółw sem yalirow sta

11 aud Įnam nions yaq Yam yoďð takið rebro al viaassoan inamyaq

bezeler að fæum varied acid äthy ömer al olvaduɗo betɔeqesno Tas

Tekno ent .asoi edd brotts Jon bingo 'rodbørðnað! exit vot

anissa ni brød reart a bebrææeb exoterend TeeniyaM taoblenk

bentaiqmo bra (*ados"dnoð" borunaim) anlægtað Frow-eosiq saed?

-revo bna shnad aid sit of sa down saw tibus to undera odið tært

-aunod evig oð sids að oð bertasb of „Erow Hood dółw mid nobruË=

sageront bus anoitibnoo xalet of snorgotq batarefèone not g#-

IlbWA Jædt bentu ek ‚„boneteter duod÷iw vissesoen ti dnompaq-

od sidaoliqqs don stew suneve♬ mort sÍïow oð: sĹdiamÅÍÇÜB, RBLIT

Smerettib yllodw alkol mi færið bra tavonsk (aðiqað morŤ KÍTOW

ort bentevon doldw snodt mort samo eno edt al sdam stew solut

.Tenfo

arið ðærið beðneygon axrow olidut to rodoerta „noĦ sdt

rot noqu boeiga mue arið saman blvode "eenkyni inobisef teiɗo

-yaq sɗd to esmeroni yna berinob od 21 Jaɗd bns Xrow-boniq edit

TonTerol edt vď bevorgqs Joette Jædd of noltabnemeooer #: #NGES»»

darið beerga I „aðnemarłuper a1rotibʊå ødt tot soittum bluow

beouber að bĺneo Xow Isoireio Visessoennu doldw yd aNGGET VILS

orutammin edt tærit ennatani tot qilatosque (sidariaab tingið Bæ

s to toot, ant da reoltto:eidianoqesi s to (ndasititres a teva)

aút gat-luper to bɛetani inaloittaa new stewodai to Ilơ% vaq

er modeva rattal sɗt no beabnt fool I „eðstoðkift done to f{"cate

JI .noaneq Inelubuætt a no Esedo a to bastani od dnsamoubat na

ert bra tervaasi? „noë eds of taloq aint retot of bestga naw

of batqoba ad trişim'ensem fariv ot na troqet not notibwa Imooi

veɗt .Írow gnitnwooda souber bra afnemertuper a'aav£ .TX Joom

lazsneg #tom edd no „min d3tw divanos od siguone boog ed IIIw nolJesup

question of Tunnel contracts, vis.:- whether larger sections

could be let to contract and whether real contracts as opposed

to what I have called the "piece-work bargain system" could be

usefully made, no definite conclusion was arrived at. Mr. Ives

stated that no contractor would look at it. I requested the Hon.

Director of Public Works to talk over the matter with'some of

the contractors whom he know, with a view to assisting the

#overnment and the Chief Resident Engineer in this matter and

to report the result. Generally speaking I gathered that the Mon. Director of Public Works was strongly of the opinion that

the work outside the Tunnel should be let out to contractors in

comparatively large contracts. In discussion with Messrs. Wolfe

and Barry I gathered -I am not sure whether 'rightly they were not at all averse to this. Mr. Eves on the other hand appears averse to such contracts and thinks he can do the work as quickly and more cheaply himself. Time is of course a very important question in the case of the Tunnel, and the capital

cost of the whole line lies out at interest until it is comTM

-pleted.

that

4. Progress reports. I had pointed out in a minute that the present progress report deals only with the bottom heading, and therefore gives no real indication of the progress of the Tunnel, and I asked for an indication of the progress in the top heading and Facing. The Chief Resident Engineer pointed out that the two latter were identical, the Facing necessarily following the Top heading as soon as the shoring was removed. He saw some difficulty in shewing progress in this matter, but after a short discussion a scheme was arrived at, which he considered quite feasible and involving no trouble, by which he would report the weekly progress in the lengths of lining

actually completed.

5.

Kr. Ives raised the question of the Hongkong-Kowloon Ferry. He said that he was now preparing the Supplemental Estimates and must know whether or not to include a wharf for steamers and cost of Steamers. That the latter would take 2 or 3 years

to

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.